You may find that you have chosen an e-house enclosure which does not allow for the replacement of a switchgear panel. This can cause delays and retrofitting.
Start by assessing your equipment layout, operational requirements, and supply scope. Then compare the structural design, cooling, inspection evidence, and cost.
Equipment Layout and Supply Scope
Will you be purchasing a bare enclosure, a fitted electrical room, or a fully equipped e-house? ABB provides an integrated eHouse solution which may include switchgear, automation cabinets, and environmental control systems.
Provide an equipment schedule detailing the dimensions, weights, door operation, and servicing requirements for each cabinet. Identify whether transformers, UPS systems, or batteries will be installed within the module.
If you have a split A and B supply design, include the required partitions and cable routes in your layout.
Ask bidders to identify the following as included, optional, or excluded:
Insulation and heating or cooling equipment.
Lighting and fire protection.
Earthing provisions.
Stairs and access platforms.
Clarify who is responsible for installing the equipment and sealing interfaces before comparing costs.
Floor Load, Structural Design & Lifting Points
A stated floor loading figure does not, by itself, confirm that the enclosure can support your equipment.
For example, a cabinet weighing 2,000 kg and occupying 2 m² would have an average static load of:
Average load = 2,000 × 9.81 ÷ 2 ÷ 1,000 = 9.81 kN/m²
The cabinet's feet or mounting rails concentrate this load. The structural designer must check their positions against the floor beams, openings, and fixings.
Request calculations covering the site's applicable wind, snow, and seismic requirements, together with transport and lifting conditions.
Confirm whether the lifting points support an empty shell or a fully equipped module. Equipment added after structural approval may change both the weight and centre of gravity.
Cooling, Ventilation & Insulation
Cooling should be sized according to the heat losses from equipment inside the enclosure. The enclosure's heat load is not the same as the data centre's IT capacity.
For an illustrative example, assume a UPS within the module supplies 500 kW at 97% efficiency at the stated operating point:
Heat loss = 500 × (1 ÷ 0.97 − 1) ≈ 15.5 kW
Obtain actual heat rejection values from the equipment supplier. Other equipment, lighting, solar gains, and heat transfer through the enclosure must also be considered. Schneider Electric discusses these factors in enclosure thermal management.
Ventilation cannot cool below the incoming air temperature. Confirm the available cooling capacity at the specified outdoor temperature and altitude, together with insulation performance, filter access, and the response to cooling failure.
Where redundancy is required, establish the remaining cooling capacity with one unit unavailable. Include alarm interfaces to the site monitoring system and access to replace a failed unit.
Fire Protection, Clearances & Servicing
Agree fire requirements with the project's fire designer. A fire-rated insulation core does not establish the rating of the complete wall, door, or penetrated assembly. Request evidence applicable to the proposed construction. UL Solutions
Refer to equipment instructions and relevant project requirements when establishing servicing clearances, escape routes, and door operation. Do not assume one aisle width suits every voltage and equipment arrangement.
Check equipment replacement access as well as routine servicing. Draw the removal route for the largest equipment section, including turning space, lifting access, and removable panels.
If switchgear requires pressure relief, coordinate its discharge route with the enclosure designer.
Weatherproofing, Corrosion Protection & Moisture
An outdoor electrical enclosure must suit the site's rain, dust, salt exposure, and humidity.
If an IEC 60529 ingress protection rating is specified, request evidence covering the final configuration of doors, louvres, and cable entries. IEC
Define corrosion protection separately, including:
Surface preparation.
Coating products.
Dry film thickness.
Curing requirements.
Repair procedures.
Review roof slopes, drainage, door sills, and the base interface. Water should drain away from entrances and cable openings.
Weatherproofing does not prevent condensation. Establish how humidity will be controlled during operation, shutdown, and storage, particularly when installed cooling equipment has no power.
Cable Entries, Earthing & Expansion
Coordinate cable routes with the electrical integrator before cutting floor or wall openings. Confirm cable bending radii, gland plates, supports, and installation access.
Specify earthing studs and bonding provisions for doors, removable panels, and module connections. The electrical designer should define the required bonding arrangement. Do not rely on incidental contact through painted fasteners.
Provide practical routes for future circuits. Unused openings need suitable closures, and later modifications must preserve weather sealing and any required fire resistance.
Agree who will seal the penetrations and who will inspect them after the cables have been installed.
Quality, Inspection & Testing
Replace a general statement such as "factory checked" with an inspection plan containing acceptance criteria and records.
The plan should cover:
Material identification and weld inspection.
Dimensional checks.
Door operation and gasket seating.
Coating thickness measurements.
Agreed water ingress checks.
Inspect interfaces against the approved equipment layout, including mounting rails, cable entries, and HVAC penetrations.
Where practical, check module-to-module connections through trial assembly. Small misalignments can become costly once the modules are on their foundations.
Establish witness points before inaccessible areas are closed. Record repairs and repeat inspections against the module's identification.
Keep enclosure acceptance separate from electrical commissioning. If another contractor installs the equipment, agree who checks bonding, cooling controls, fire systems, and completed penetrations.
Cost per Kilogram, Lead Time & Responsibilities
For quotations priced per kilogram, agree on the billable weight basis. Does it cover fabricated steel only or the finished assembly? Compare the same drawing revision and supply scope.
The following figures are illustrative, not market quotations:
| Cost Item | Supplier A | Supplier B |
|---|---|---|
| Agreed billable weight | 8,000 kg | 8,000 kg |
| Price per kilogram | USD 2.50/kg | USD 2.70/kg |
| Base amount | USD 20,000 | USD 21,600 |
| Required coating upgrade and packing | USD 2,600 | Included |
| Comparable subtotal | USD 22,600 | USD 21,600 |
Freight and taxes are excluded. Although Supplier B charges more per kilogram, its comparable subtotal is USD 1,000 lower.
More steel does not automatically mean better performance. Accept additional steel when the structural design requires it.
Confirm milestones for manufacturing, inspection, packing, and delivery. Distinguish factory completion from arrival on site, and establish what triggers the start of production.
Send the same drawings to shortlisted suppliers and request a priced deviation list. Attach the agreed supply scope, inspection plan, billable weight basis, and delivery schedule to the purchase order.